June 2009
Permits
Issued
First Plans Complete
Phase I Started
July 2009
Construction Started
August 2009
Construction Celebration
Kick-off Founding Member Campaign
Building layout complete
September 2009
Footers and Foundation Complete
Structural Work Started
October 2009
Rough in plumbing in place
Rough in electrical conduit in place
Curb and Guttering started
Slabs Poured
Gymnasium walls up
Racquetball court walls up
Structural steel onsite
Exterior walls and Locker room walls started
Ballfield grading underway
November 2009
Block work continues
Gym roof trusses in place
Locker room walls up
Parking lot sub base in place
Slabs complete
December 2009 - Percent complete
Bonds & Permits @ 100%
Sitework @ 72%
Landscaping @ 3%
Concrete @ 86%
Masonry @ 77%
Steel/Miscellaneous Metals @ 80%
Wood/Carpentry @ 14%
Roofing/Sealants @ 25%
Doors/Storefront @ 9%
Finishes @ 8%
Specialties @ 0%
Athletic Equipment @ 0%
Appliances/Kitchen Equipment @ 0%
Pools/Sauna @ 5%
Fire Protection @ 21%
Plumbing @ 43%
HVAC @ 18%
Electrical @ 40%
Change Order 1 100%
Change Order 2 91%
January 2010
Steel erection progressing; completion likely 2-4 wks
Concrete masonry block work ongoing; likely complete by February.
Installation of roof decking proceeding; following along behind steel
Roof at gymnasium complete.
Brick work proceeding as possible due to weather.
Installation of modified bituminous roofing membrane will begin shortly.
Duct work installation underway; coordination discussions were held.
Roof leader piping underway; coordination discussions were held.
Sprinkler piping shall begin in roughly 3 weeks.
Fall 2010
Projected Completion
|